Projects

Here are sample projects in the field of construction and modernization of high-voltage and medium-voltage lines, as well as power substations:

Construction of the Cisna Energy Storage Facility, including the complete modernisation of the existing 30/15 kV network substation and the design and construction of a fibre-optic network for control and monitoring purposes

Investor:

PGE Dystrybucja S.A. Oddział Rzeszów

Carrying out construction works relating to the construction of 110 kV and 15 kV cable lines, including fibre-optic cable, and the comprehensive design and installation of a DTS system between the 110/15 kV Legionowo B and Legionowo Cegielnia substations

Investor:

PGE Dystrybucja S.A. Oddział Warszawa

Carrying out construction works within the operational area of the Łódź Branch of RE Łódź: “Construction of a 110 kV cable line between Srebrna and Koziny (Completion of the 110 kV Power Ring – sections 2 and 6)”

Investor:

PGE Dystrybucja S.A. Oddział Łódź

Design and execution of an EPC power connection (Task No. 5) and design and execution of works in the power sector, I&C and system engineering (SCADA) within Tasks No. 1 to 4 and No. 6, as well as provision of the Service for a period of 10 years from the date of Takeover into Operation within the aforementioned Tasks No. 1 to 6.

Investor:

Ostrowski Zakład Ciepłowniczy

Construction of the 110kV Barlickiego station.

Investor:

ENEA Operator Sp. z o.o.

Modernization of the 110/15 kV RPZ-9 Białystok power station, in accordance with the available design documentation

Investor:

PGE Dystrybucja S.A Oddział Białystok

TMFW BAŁTYK II Offshore wind energy project, design of electrical installation and onshore power station EPC

Investor:

Polenergia S.A.
Equinor Wind Power AS

Construction of an 8 MW/8 MWh energy storage facility and the RS Smolnica SN-15 kV network switchgear, along with the demolition of the old network switchgear and the construction and reconstruction of SN-15 kV cable lines

Investor:

ENEA Operator Sp. z o.o.

Design documentation – 110 kV Wilanów-Siekierki line

Investor:

Stoen Operator Sp. z o.o.

Construction of the 110/15kV GPZ Rozwadów power station

Investor:

PGE Dystrybucja S.A.

Construction of the 110/15 kV RPZ-5 Białystok power station with a 110 kV GIS switchgear

Investor:

PGE Dystrybucja S.A.

Expansion of the existing 110 kV Polichna switchgear with 110/15 kV power transformers and a 15 kV switchgear.

Investor:
PGE Dystrybucja S.A.

Modernization of 110kV cable lines in the Żarnowiec Substation

Investor:
Polskie Sieci Elektroenergetyczne S.A.

Reconstruction and expansion of the Trzy Korony hotel and restaurant in Puławy

Investor:

Elektropaks Sp. z o.o.

Drilling works –IPA A-Nord project (04-01)

Investor:

Amprion

Drilling works –SuedLink Los 8

Investor:

TRANSNET BW / STRABAG/ KRAFTEAM

Drilling works –SuedLink PFA 3

Investor:

TENNET / ARGE

Development of design documentation for the construction of the 110/15kV Lubartów Południe substation.

Investor:

PGE Dystrybucja S.A.

Reconstruction of the 110kV R-2 Czechnica station and addition of a 110/20kV transformation

Investor:

Tauron Dystrybucja S.A.

Thermal modernisation and renovation of buildings in the warehouse area at the 400/220/110kV Kozienice station

Investor:

PSE S.A.

Construction of a 110kV cable line on the Łomianki-Czosnów route

Investor:

PGE Dystrybucja S.A.

Construction of a double-circuit 110 kV cable line: RPZ Gdańska – EC Żerań on the section between the planned cable poles no. 15 and 23 and RPZ Wschodnia – EC Żerań on the section between the planned cable poles no. 29 and 37.

Investor:

Stoen Sp. z o.o.

Construction of the 110/15kV RPZ Tarchomin station

Investor:

Stoen Sp. z o.o.

Construction of the 110/15kV GPZ Czosnów station

Investor:

PGE Dystrybucja S.A.

Construction of the 110/30kV Sgs-6 Osiny station

Investor:
PGE Górnictwo Energetyka Konwencjonalna S.A.

Expansion of the 110/15kV Staroniwa Rzeszów station

Investor:

PGE Dystrybucja S.A.

Expansion of the 110/15kV Centralna Rzeszów station

Investor:

PGE Dystrybucja S.A.

Design and reconstruction of the 110/15/10kV Lublin Dziesiąta station

Investor:

PGE Dystrybucja S.A.

Design and construction of the 110/15kV Bursaki station

Investor:

PGE Dystrybucja S.A.

Modernization and reconstruction of the 110/15kV Gorzyce station

Investor:

PGE Dystrybucja S.A.

Construction of the 110/15/6kV RPZ Polesie station with connections on the HV and MV sides

Investor:

PGE Dystrybucja S.A.

Extension of the 15/15kV RSM Cybernetyki power station to a 110/15kV station, stages I and II

Investor:

PGE Dystrybucja S.A.

Cabling of the 110kV line between Kawęczyn and Miłosna

Investor:

Stoen Sp. z o.o.

Reconstruction and extension of GPZ KZWM Kielce

Investor:

PGE Dystrybucja S.A.

Construction of the 110/15kV Banie Mazurskie station

Investor:

PGE Dystrybucja S.A.

Construction of the 110/15kV RPZ Ursus Miasto power station

Investor:

Stoen Sp. z o.o.

Construction of a 110kV cable line, a DTS system, and a fiber-optic line between R-106 Żelazna and R-134 Skarbowców in Wrocław

Investor:

Tauron Dystrybucja S.A.

Construction of the 110/6kV “Bzie” power station and the main 6kV “Bzie” switching station in the “Borynia-Zofiówka” coal mine, Ruch Zofiówka

Investor:

Jastrzębska Spółka Węglowa S.A.

Modernization of the 110kV switchgear at the 110/6kV PODLESIE substation

Investor:

PGE Dystrybucja S.A.

Construction of a new GPZ-3 at the CHP plant in Płock.

Investor:

Orlen S.A.

Reconstruction of the 110/20/10 kV R-105 Wrocław Swojec station

Investor:
Tauron Dystrybucja S.A.

Construction of the 110/15kV Euro-Park 1 substation
Stalowa Wola

Investor:

PGE Dystrybucja S.A.

Reconstruction of the 110/15kV GPZ Końskie Stary Młyn station

Investor:
PGE Dystrybucja S.A.

Replacement of 6kV cables from GPR-P4 and GPR-P3

Investor:

Orlen S.A.

Construction of a double-track 110kV Czosnów-Legionowo-Nowy Dwór Mazowiecki line with a crossing of the Vistula River

Investor:

PGE Dystrybucja S.A.

Construction of a double-circuit 110kV Mościska-Łomianki line

Investor:

PGE Dystrybucja S.A.

Construction of the 110kV Łąkowa-Śródmieście-Drewnowska line

Investor:

PGE Dystrybucja S.A.

Construction of power lines for the GSZ 20/6 kV “Szyb Grzegorz” station

Investor:

TAURON Wydobycie S.A.

Cable lines

ELEKTROPAKS company implemented a project under Priority Axis 4 Environmentally Friendly Energy, Action 4.2 Energy Production from RES in Enterprises, Regional Operational Programme of Lubelskie Voivodeship for 2014-2020